(Third
Army Location: St. Jacques de Nehou)
(7
July 44 - 1 Aug 44)
The 33rd Signal Construction
Battalion landed at Utah Beach, Cherbourg Peninsula, on July 7, 8,
and 9, 1944, and proceeded to its first bivouac in the area
northwest of St. Jacques de Nehou and south of Bricquebec. At
this time Third Army Headquarters was being established two miles
east of St. Jacques. This Battalion installed the trunk line
between the Army Command Post and the rear echelon and ran local
lines within both areas. This was not normally our duty, but
at the time the 33rd was the only Signal unit with the equipment and
material to do the job.
Four crews were detached to Army
Headquarters to set up and operate construction centers (wire
heads). These crews installed the Lucky (Third Army) and Lucky
Rear wire heads in dugouts and remained to operate the Lucky wire
head and maintain Lucky lines. The Lucky Rear wire head was
taken over by another unit.
Some Third Army units were
already in France, and our crew provided communications to other
units each day as they arrived. A switching central (Oraille
Switch) was established at Battalion Headquarters, and men from
Headquarters Company were quickly trained as operators (T/O 11-25
does not provide for switchboard operators). These men were
later replaced by operators from the 301st Signal Operation
Battalion.
It was soon determined that for
efficient operation, a central control point was necessary in order
to coordinate the various jobs and dispatch crews. Therefore
each construction company established a wire operations center for
this purpose. A noncommissioned officer was placed in charge
of each operations center, with one assistant and a draftsman.
In order to keep abreast of the current status of all crews, a
card system was established. One card was made for each crew,
listing the number of the crew, type of equipment, type truck,
members of crew, etc. These cards were hung on a dispatch
board, which was divided into sections indicating crews in or out.
Separate smaller cards were made to be used on the
"IN" side of the board to indicate further each crews
status, such as Guard, Alert, Rest, etc. For example if a crew
was on guard duty their card would be hung on the "IN"
side of the board with a smaller "Guard" card placed on
top of it. In conjunction with these cards, a daily sign-out
sheet was kept, showing the crew number, date, job number, time
dispatched, and time returned. In order to make sure that
administrative details would not conflict with construction
activities, all rosters (guard, K.P., etc.) were either maintained or
supervised by the operations center. Records were kept showing
progress of each job, and upon completion an overlay was prepared
for the information of higher headquarters. Similar records
were kept on maintenance of existing lines.
An officer was attached to the Army
Signal Section to act as Liaison Officer. His Duties were to
transmit orders from the Signal Section to the Battalion and to
furnish the Signal Section with any information it might require in
regard to material, personnel, and equipment available in the
Battalion. He kept in close contact with the operations
centers, transmitted construction orders to them, and received
progress reports, etc. for them.
Rehabilitation work was immediately started
on the German Naval lead, a line left by the Germans which started
at Cherbourg and extended south through Coutances. Originally
the crews started using all the existing materials, but after
rehabilitating about two miles it was decided that, due to the
damaged condition of the wire and the unfamiliar transposition
scheme, it would be better to use only the poles. Two standard
ten pin cross-arms and .104 copper wire would be placed on these
poles, and the Army axis of wire communication was to be extended on
this lead when we moved forward. As this lead was across
country, progress of the work was hampered by hedgerows, which
either necessitated long detours for the trucks or prevented their
access to the line altogether, making it necessary at times to pull
in wire by hand. At one time horses were borrowed from French
farmers to pull in wire in places inaccessible to trucks. Later a
bulldozer was obtained and used to cut a path through the hedgerows
so that trucks could be driven beside the lead for its entire
length.
Inasmuch as the Army
Signal Section desired up-to-the-minute information on the progress
being made on this line, a system was devised whereby the line crews
would place a white flag on the top of the last pole to which the
line had been completed. A reconnaissance plane (L-4 or L-5)
would fly over the line until he spotted the flag, and the report
the position by radio.
Upon completing our first
section of the line (Bricquebec to St. Sauveur) Company B moved to
the vicinity of LaHaye du Puits. The section between St.
Sauveur and La Haye was completed by the 34th Signal Construction
Battalion. They continued the work of extending the lead from
La Haye du Puits south as far as the tactical situation would
permit. Here they were under enemy observation, and artillery
barrages were frequent. This was our first experience under
shellfire. The men slept in covered foxholes, and the loss of
sleep due to artillery fire caused a lowering of efficiency on the
job. The line was damaged by shellfire several times.
A number of field wire lines
were also constructed during this period, and some wire was
recovered (see S-3 report for July, 1944)
The original plan for the Third Army
was to maintain the advance with Corps abreast: XV Corps on the left
flank, XX Corps in the center, and VIII Corps on the right flank.
The Army Axis was to be extended on the open wire lead
following XX Corps, and spiral-four cable was to be laid to the
flanking Corps.
The open wire lead was extended
to Lessay Test, about half way between La Haye du Puits and Lessay.
The XV Corps went into operations July 32, and moved to the
vicinity of St. Martin d'Aubigny. Fifteen miles of spiral-four
were laid from Lessay Test to this location. This was our
first rapid spiral-four construction job, and was completed two
hours ahead of schedule.
At the time of the August 1st
breakthrough our efforts to extend the open wire lead south as
rapidly as possible were redoubled. However, there was a
bottleneck at Lessay. The enemy had been in fixed positions
here for sometime, and had covered the countryside with mines.
One crew was detailed to detect and clear mines along the
right-of-way ahead of the construction crews. Thirty-eight
mines were removed from the pole line right-of-way in a single
afternoon.
Communication to the new Army CP at
Bingard was established by another unit, using spiral-four from
Lessay Test. Meanwhile this Battalion (Less Company B) moved
to Montsurvent, 1 1/2 miles from the Army CP. Company B
remained at La Haye.
(Third
Army Location: Bingard)
(1 Aug. 44 - 2 Aug. 44)
(24
miles from St. Jacques de Nehou)
Immediately upon arrival at this
location, plans were made to move again the following day, as the
Corps were already far ahead. This Battalion was assigned to
continue work on the open wire lead while the 34th Signal
Construction Battalion extended the Army axis with spiral-four.
(Third
Army Location: Beauchamps)
(2 Aug. 44 - 7 Aug. 44)
(22
miles from Bingard)
As it was now obviously
impossible to extend the Army axis fast enough on open wire it was
decided to stop work on it at Coutances by first bringing one arm of
wire through to that point. This would give us five circuits
until the second was brought up, and then the line would be taken
over by Com Z troops.
At this time one officer and four
crews were dispatched to
XV
Corps to establish and maintain Army-Corps communications (see
notes on "Detachment with XV Corps").
Company B completed it section of the
open wire lead, and with Battalion Headquarters moved to a bivouac
three miles north of St.James, from which they could work on a
further extension of the Army axis. Two teams were on detached
service at the Beauchamps wire head. Two spiral-four cables
were laid from Beauchamps through Avranches and St. James to
Fougeres. The roads were jammed with trucks and tanks; traffic
would often be stalled for 20 to 30 minutes, making construction
work very slow. Lines in the process of construction were
frequently cut by tanks before the crews were able to put them in
the air. It was necessary to reroute the lines twice at
Avranches because they were being hit by bombs near the river
crossing. Collaborators were prevalent in and around the city,
and our cables were cut many times, making constant patrols
necessary.
Company A completed the open wire lead to
Coutances and joined the rest of the Battalion at the St. James
area. At this time the enemy was endeavoring to push through
Avranches to the sea and thereby cut off the advance elements of the
Third Army. Constant alertness was necessary on the job, and
in bivouac. Enemy aircraft attacked this area dropping
antipersonnel bombs.
Spiral-four cable and field wire became
scarce and in spite of the desperate need for construction crews, it
was necessary to send a section of one platoon back to St. Jacques
to recover wire.
(Third
Army Location: Poilley)
(7 Aug 44 - 11 Aug 44)
Spiral-four cables extending south
from Beauchamps had been completed before Army Headquarters moved to
Poilley; thus wire communications to the rear were established by
means of spiral-four to Coutances, where it tapped on to the open
wire lead.
The extension of the Army axis in
preparation for the next move was done by the 34th Signal
Construction Battalion. Several long locals were installed by
the 33rd in this vicinity.
(Third
Army Location: St. Ouen)
(11 Aug 44 - 14 Aug 44)
(35
miles from Poilley)
In order to be more conveniently
located for additional construction ahead of the Army CP, this
Battalion moved to St. Jean, about 29 miles from St. Ouen, between
Laval and LeMans. Here we started to put in a two-circuit
bracket lead on existing poles along the road from Laval and LeMans,
filling in the gaps by replacing poles where necessary. Lack
of materials forced us to abandon this job and look for existing
facilities to fulfill our requirements. Two days had been
wasted on this work, so it was now necessary to produce wire
communications as quickly as possible. Extensive surveys of
existing civilian facilities were made, which showed that
underground cable could be rehabilitated and used for army circuits,
as well as an open wire lead along the railroad from Laval to LeMans,
although portions of the latter were still in enemy hands. Our
cable crews were called into action, and they made the underground
cable good from Laval to St. Jean, a distance of 17 1/2 miles.
Inasmuch as our cable splicers' tool kits had been
received incomplete, each cable splicer had only a hammer, knife,
telephone(EE8A), some tape and whatever he could get from the line
crews.
As soon as the enemy was cleared
from Evron and Sille, the French open wire was rehabilitated along
the railroad from Laval to LeMans (54 miles). This lead had been
bombed out at all towns and railroad stations, as well as numerous
other points. Breaks were patched through with field wire and
spiral-four cable. Maintenance of this line was difficult
because of it inaccessibility to trucks.
Orders were received to have
communications completed for a new Army CP at La Bazoge (north of
LeMans) by 1200, August 14. Spiral-four was laid from the
underground cable terminal at St. Jean to La Bazoge, and also from
the French open wire on the railroad near La Chapelle to the
proposed location.
As the speed of the advance increased
the lines of wire communication became exceedingly long. While
Army Headquarters was at this location, VIII corps was at Miniac
Moran(75 miles away), XV Corps was east of Alencon (45 miles away),
and XX Corps was just southwest of La Ferte Bernard (28 miles away).
(Third
Army Location: La Bazoge)
(14 Aug 44 - 20 Aug 44)
(56
miles from St.Ouen)
After trunk lines to this
location were completed the Battalion move to the vicinity of Nogent
le Retrou (39 miles from the Army CP) on August 15. Again the
Battalion was bivouacked ahead of the Army CP to facilitate pushing
forward the Army axis.
For some time we had been trying
desperately to either requisition or borrow cable splicers'
kits, but none were available anywhere. Finally kits were
borrowed from the 93rd Signal Battalion. This was very
fortunate, as a great deal of work was done on underground cable,
and it formed a very essential part of the wire system. Underground
cable was made good from LeMans to La Bazoge to Alencon (30 miles),
from La Bazoge to LeMans to Nogent le Rotrou(39 1/2 miles), and the
city tie cable in LeMans was also made good so that these wires
could be cross-connected.
Spiral-four cable was laid from
La Bazoge to Savigne Switch to connect with XV and XX Corps.
While Third Army was at this
location XV Corps advanced north to assist in closing the Falaise
Gap, and wire communications to it were discontinued, as they also
were to VIII Corps which was at Brest. XII Corps joined the
Army advance and moved up just southeast of LeMans; XX Corps was 62
miles from La Bozoge. The XX Corps line was too long for
satisfactory transmission, and no carrier or repeater equipment was
available, so it was routed through Nogent Switch and calls were
relayed by the operator. Nogent Switch, operated by Company A,
was also connected in the Lucky-Hickory (XV Corps) circuit until
service to Hickory was suspended. There being no switchboard
operators in the company, it was necessary to train operators while
actually on the job.
(Third
Army Location: Brou)
(20 Aug 44 - 25 Aug 44)
(66
miles from La Bazoge)
The Battalion was given 36
hours notice on the job of installing wire communications from La
Bozoge to a point about three miles west of Chateaudun, which was
the proposed new CP for Army. However we already had
spiral-four and underground cable circuits to Nogent le Rotrou, and
civilian facilities beyond this point had been surveyed in
preparation for a move. One spiral-four cable was laid from
the underground cable terminal at Nogent to the French open wire
railroad lead. Two open wire circuits were made good from
Nogent to Authen to Royale to Courtalain to Chateaudun, and extended
to the new CP with spiral-four. Just as this work was
completed, word was received that the location of the CP had been
changed to a point just northeast of Brou. Wire
communications were completed to the new CP on the same day in spite
of the change. This was done by tapping spiral-four on the
open wire lead at Royale. Two existing open wire leads were
used with spiral-four filling in the gaps between Royale and the new
location(10 miles). It was necessary to put the last four
miles of spiral-four on lance poles to get it off the ground. Later
four additional open wire circuits were made good from Nogent to
Arrou to Brou. While on this job we encountered a ground on
the open wire, and found that on a frame poles constructed at
corners the wire on the bottom bracket nearest the pole touched the
push-brace. It was necessary to examine every corner pole on
the line to reduce the ground so that transmission was satisfactory.
Open wire was also rehabilitated from Chateaudun to Bonneval
to Brou.
After completing communications to the
Army CP at Brou, the Battalion moved there to join Army
Headquarters. The same day Company A was attached to XX Corps
at Oysonville, near Etampes, to extend Corps communication along the
Army axis, and to maintain communication between Corps and Army.
At this time Corps was moving very fast, and the company was
engaged exclusively in extending lines along the axis of
communication with spiral-four.
Spiral four cables were placed between
Brou and Pithiviers by other units, and this Battalion extended this
line on rehabilitated open wire and spiral-four to the new Army
Location at Courcy.
(Third
Army Location: Courcy)
(25 Aug 44 - 30 Aug 44)
(68
miles from Brou)
The Battalion (less Company A) moved
to Montvillers on August 23, and immediately started work on
communications from Courcy to Nogent-sur-Seine. This was
established on rehabilitated open wire and spiral-four construction
through Nemours. Several local lines were installed in this
vicinity.
Underground cable was made good from
Nemours to Bourron, and from Moret to Montereau to Sens.
At this time gasoline was scarce and
we barely had enough for the next move.
(Third
Army Location: Foret de Lancy)
(30
Aug 44- 4 Sep 44)
(77
miles from Courcy)
This Battalion (less Company A) moved
to Couregenay on August 30, the same day of the Army move. Communications
to the New Army CP were established by running six spiral-four
cables to Nogent, where lines had already been established back to
the old location.
By this time the gasoline shortage was
at its peak. One crew installed a talking circuit from Lucky
switchboard to a gasoline depot near Fontainebleau by using
spiral-four, underground cable, and open wire. As it was
impossible to obtain gasoline in this area, and a truck was sent
back to Cherbourg, nearly 300 miles, for gasoline.
During this period our cable crews
were being used extensively in the rehabilitation of underground
cable. Their rehabilitation of the Troyes-Chalons cable
provided a major portion of circuits to the advanced CP. An
open wire lead from Villeneuve to Troyes was made good, and the
remainder (i.e. old CP to Villeneuve, and Chalons to new CP) was
filled in with spiral-four cable. On September 4, the 33rd
moved with Army Headquarters to the vicinity of Chalons-sur-Marne.
(Third
Army Location: Chalons-sur-Marne)
(4
Sep 44-15 Sep 44)
(88
miles from Foret de Lancy)
Inasmuch as convoys moved very
slowly along the busy roads, it was found more efficient to move to
the new bivouac by infiltration. The vehicles would move out
in small groups, and those crews which were on the job could join
the company at the new location after finishing their current jobs.
This practice was continued on subsequent moves. Battalion
Headquarters and Headquarters Company moved to Regret on September
5, to join Company A. Company B remained with Army.
Circuits were made good on a German
open wire line from the Valmy repeater station to Auve. From
there the line split into two sections, one extending back toward
Chalons, and the other southeast to Revigny. Our crews
rehabilitated both of these sections, one of which was used for
circuits from the Army CP to Valmy.
During this period our cable crews
rehabilitated underground cable from Chalons to Reims (37.8 miles),
Reims to Valmy (39 miles), Valmy to Verdun (32 miles), and Verdun to
Gravelotte (30 miles). On the total job, which was completed
on September 7, four quads were made good from Chalons to Gravelotte.
Due to the fact that Gravelotte was retaken by the enemy, that
terminal had to be abandoned. The cable was later opened and a
terminal point established just east of Mars la Tour to serve XX
Corps.
The Chalons-Verdun section of this cable was
utilized in establishing communications with the new CP near Etain.
From Verdun there was two alternate routes: (1) continuing
along the underground cable to a terminal at the junction of
highways N3 and N408, to which another unit had provided spiral-four
circuits from the new CP; ( (2) open wire was made good from
the underground cable terminal at Verdun to Etain. Third Army
Headquarters moved to the new CP on September 15.
(Third
Army Location: Braquis and Etain)
(15
Sep 44 -11 Oct 44)
(65
miles from Chalons)
Shortly after the Army's move, Lucky
Rear moved to an area four miles north of Etain. The big push
was stalled at Metz and a few miles east of Nancy, and the cold
weather was coming on, so it was decided to move the army
installation into billets. A third echelon of Army
Headquarters, Lucky Command, set up in Etain on September 22, and
the old Lucky CP at Braquis gradually moved into Etain to join Lucky
Command. Our Crews installed and operated the Lucky Command
wire head in Etain.
Company B had moved to this vicinity
September 14, but it was necessary to leave several crews in the
area of the old CP to pick up wire, which was still scarce. Work
on the French open wire lead was continued, and it was made good
from Etain through Jarny to Mars la Trou, to serve for alternate
circuits to XX Corps. Other circuits to this Corps utilized
the underground cable from the N408 terminal point. Later this
Battalion rehabilitated the lead from Mars la Tour to Arnaville.
This provided circuits from Lucky to Arnaville test, from
which we laid two spiral-four cables through Pont-a-Mousson to
Nancy, to connect with XII Corps. While these lines were being
constructed along the Moselle the enemy was only a short distance
across the river; the line crews were frequently under fire from the
enemy's 88mm guns, and these cables were constantly being knocked
out. Long range fire from 280mm guns also damaged the lines.
The 34th Signal Construction Battalion laid two Spiral-four
cables from Etain to Arnaville to connect with our cables to Nancy,
for carrier circuits to XII Corps. Our crews rerouted this
cable between Chambley and Arnaville, as it was continually being
knock out by enemy fire in this section.
Battalion Headquarters and
Company A were at this time bivouacked between Mars la Tour and
Jarny. An open wire lead was rehabilitated from Verdun to the
N408 cable terminal point. Wet weather set in, and mud
Hampered our operations considerably at this time. The french
open wire along the railroads was particularly troublesome in wet
weather. It was in general poorly insulated, and the
collection of soot on the insulators from passing trains became an
excellent conductor when wet, forming a perfect path to ground
through the metal pins and cross arms. The only satisfactory
way to remove the grounds from these lines was to wipe each
insulator with carbon tetrachloride-- a slow and tedious process.
Cracked insulators also caused trouble in bad weather.
Battalion Headquarters and
one platoon of Company A moved to Pont-a Mousson on October 1.
During this time Pont-a-Mousson was under fire from the
enemy 280mm guns.
Communications were
established with spiral-four cable from Lucky to Etain to Lucky
Baker switchboard at Foug, where communications had already been
established to Nancy. Thus were two Alternate lines to the
advance Army CP at Nancy; one through Lucky Baker, and the other
through Arnaville Test on the XII Corps cables.
(Third
Army Location: Nancy)
(11 Oct 44 -23 Dec 44)
(57
miles from Etain)
One platoon of Company B had
moved to Nancy on September 27, and was attached to XII Corps.
They Placed ten spiral-four cables on two No. 9 iron wires
from the Nancy West wire head to Lucky Advance in the center of the
city, and also to the radio link. Communications were
established with XV Corps on the right flank and XX Corps on the
left by means of spiral-four cable. Open wire along the
railroad was rehabilitated from Nancy east to Moncel; this lead was
in very poor condition, and required almost total replacement of the
wire, as well as numerous poles. Due to the static tactical
condition at this time, the platoon moved to Pont-a-Mousson (about
October 20) to join the Battalion Headquarters. Company B's
second platoon had remained at Etain after the Army's displacement
to pick up wire and to maintain communications in that area. The
second platoon of Company A moved from Pont-a-Mousson to Joeuf, near
Briey, at this time, and the remainder of the company stayed with
Battalion Headquarters at Pont-a-Mousson.
During the long stay of Third
Army in the Nancy area a very elaborate communications system was
setup. Such an elaborate system was never contemplated during
training. The 33rd operated a switching central (Lone star
Switch) at Pont-a-Mousson during this period.
Company A's platoon at Joeuf
constructed Third Army's first BMAL (British Multi-Air Line) lead in
France, from Conflans to Briey. In spite of there inexperience
with this type of construction, the lead was quickly finished, and
gave very little trouble.
Company B added a second arm on
an existing Army pole line from Hannoville (near Mars la Tour) to
Couflans; Company A extended this second arm north to Fleville, and
from there built new pole line to Thionville. The mud
situation was at its worst at this time. The line was not
built along roads, therefore some sections of it became impassable
to trucks because of the mud. One platoon managed to borrow a
"Weasel" (personnel and cargo carrier M-29-C) from another
unit, and later these vehicles were issued to both construction
companies. They were extremely useful in hauling materials along the
line, and also for pulling wire.
On November 8, Battalion
Headquarters and part of Company A moved to Tucquegnieux, northwest
of Briey. From here work was continued on the
Fleville-Thionville open wire lead. Meanwhile one platoon of
Company B was again attached to XII Corps. At this time
Company B had six teams and six NCO's of the first three grades
operating wire heads: Lucky Command, Lucky Baker and Lucky
Charley. Another signal unit had completed an open wire lead
from Nancy to Moncel, and our crews extended this line with
spiral-four to Chateau Salins for the next Corps move. The
cable was laid along a main supply route which was very narrow and
had heavy traffic. For additional circuits, rehabilitation of
the French open wire was continued from Moncel to Chateau Salins.
This platoon moved
to Chateau Salins on November 14 and started establishing two
alternate routes of communication to Morhange; one on spiral-four
up the main road, and the other on rehabilitated French open
wire along the railroad to Conthil,
and
then to Morhange on spiral-four cable. Open wire circuits on
the Army axis were being pushed forward, and as sections were
completed they were put into operation in lieu of the spiral-four
cable. This not only improved transmission, but also released
the cable for further use.
XII Corps moved to
Morhange, and the Corps axis was extended with spiral-four to
Sarralbe. Two groups of open wire along the railroad were also
made good to this point. Near Morhange one of our trunks
struck a mine and was completely destroyed. Two men were
slightly injured. Spiral-four cable was laid from St. Avold to
Sarralbe. When Corps displaced to Sarralbe the axis was
further extended be rehabilitating open wire to a road junction two
miles east of Sarreguemines. Spiral-four was also placed from
Sarreguemines to Merlebach, northeast of St. Avold.
The first platoon of Company A moved
from Tucquegnieux to Basse Yutz, a suburb of Thionville, on November
24. On December 1 the second platoon also moved to Basse Yutz,
and Company A began extending the open wire construction from
Thionville to Bouzonville. This lead was built through a heavily
mined area. Personnel were obtained from the 88th and 179th
Engineer Battalions to clear the right-of-way of mines. The
second platoon was assigned to work from Bouzonville, and moved
there December 8. This job was finished on December 20. Spiral-four
was placed from Bouzonville to Ittersdorf, Germany.
On December 1, Battalion Headquarters
moved to Pont-a-Chaussy, east of Metz, and was joined there by the
first platoon of Company B. This platoon laid spiral-four
cable from Conflans through Metz to Courcelles Chaussy. At
this time three forts were still holding out in Metz, and great care
had to be taken to prevent contact with the enemy. Roads were
heavily mined, and these forts commanded most roads leading into
Metz. They completed this job and then extended the cable on
to St. Avold.
At this time Third Army moved north to join in the
Battle of the Bulge, thus ending the Campaign of France.
OPERATIONS
OF COMPANY "A" WITH XX CORPS
(21
Aug 44 - 8 Sep 44)
On August 21 Company A left the Battalion bivouac
near Nogent le Rotrou to move with the Battalion to the vicinity of
Brou. Upon arriving at the new bivouac the company was
instructed to report to XX Corps. At that time the Corps was
located at Oysonville (near Etampes); Company A established a
bivouac at Chalou. From this time through the remainder of the
"big push", the principal mission of the company was to
extend Corps communication along the proposed Army axis. Between
August 21 and September 1 the company occupied six different bivouac
areas; Chalou, Nilly, Fontainebleau, Donnemarie, Montmirail,
Louvious, and Chaudefontaine (near St. Menehould). During all
of these moves the company kept XX Corps in communication with Army
and continued pushing the axis forward with spiral-four cable.
At Fontainebleau it was necessary to establish alternate
routes across the Seine on two different bridges.
These rapid moves made the supply situation
extremely difficult, as only two trucks were available for hauling
signal supplies. In addition to hauling supplies from the
Signal Depot, these trucks had to shuttle the materials from area to
area. With this shortage of transportation, on occasions we were
required to have men in three different areas guarding supplies.
On September 1, upon reaching the area
near St. Menehould, the company was halted for lack of gasoline, and
for a few days was unable to do any line work other than necessary
maintenance. The gasoline shortage was so acute that even for
necessary maintenance only ¼ ton trucks were used. After the
gasoline shortage had been somewhat alleviated a German military
lead was rehabilitated from St. Menehould to Verdun to provide
communications to the New Corps location. On September 5 the
company moved to Regret, near Verdun, and the next day Battalion
Headquarters and Headquarters company moved into the same area. The
French open wire lead along the railroad from Verdun to Jarny was
made good to furnish circuits to the general area where XX Corps
expected to move. Corps Headquarters moved to the vicinity of
Mars la Tour, and tapped on to the underground cable for circuits
back to Verdun. At the same time Headquarters and Company A
moved to a bivouac area between Mars la Tour and Jarny. Company
A immediately started rehabilitation of the Mars la Tour-Jarny open
wire lead to provide an alternative circuit to XX Corps. At
this time the siege of Metz had halted the progress of the Third
Army, and XX Corps was closer to Army Headquarters then they had
been at any time since Normandy.
DETACHMENT
WITH VIII CORPS
(14 July 44-15 Sept 44)
One officer and 34
enlisted men (four crews) from Company B were dispatched to VIII
Corps on July 14, equipped with two line trucks (K-43), to 2 ½ ton
6x6 trucks, and one ¼ ton truck. Their mission was to
maintain communications between the Corps and First Army, and they
joined the Corps in a bivouac area near La Haye do Puits, being
attached to Company C, 59th Signal Battalion. Communication to
First Army had already been established by a First Army unit, using
an open wire lead from La Haye to St. Sauveur le Vitcomte to Chef du
Pont and thence along a railroad to Carentan, and the detachment's
original job was to maintain this line. When the
breakthrough was made at Lessay, Corps moved to the vicinity of
Geffosses (15 miles); the detachment provided communications from
the old CP with spiral-four cable. The next day, August 1, the
Corps moved to St. Sauveur le Pesnel (23 miles), to which
spiral-four was also laid. At this time VIII Corps was under
the control of Third Army. Again on August 4, Corps
Headquarters moved to Sartilly, and the detachment laid spiral-four
cable back to meet crews from the 34th Signal Construction Battalion
who were bringing cable up from the old location. At this time
the detachment's two cargo trucks were used by the Corps Signal
Section to haul cable, and when they returned they immediately
started laying cable to Vergoncy (near St. James), where Corps moved
August 7. There was only one route to lay the cable through
Avraches, and consequently the line was bombed out so frequently
that it was necessary to bivouac teams along the line to keep
communication in. On August 9 the detachment moved with Corps
Headquarters to Miniac Moran (25 miles), and lead spiral-four cable
to St. James; from there it was extended and maintained to Third
Army by the 33rd Signal Construction Battalion. Our detachment
also rehabilitated a German open wire lead form Miniac Moran to
Alabama Switch in Avrances, where it could be switched through Eagle
(Twelfth Army Groups) to Lucky as an alternate route. At the
fall of St. Malo VIII Corps was to move to the vicinity of Brest.
Realizing that the distance was too great to be bridged with
spiral-four, the detachment commander reported to Army Headquarters
for instructions. He was instructed that the detachment would
remain with VIII Corps, but wire communications with Army would be
suspended temporarily. The detachment accompanied Corps
Headquarters to Ploudaniel and was placed at the disposal of the
Corps Signal Officer. There they rehabilitated and maintained
a German open wire lead to the outskirts of Brest, reconnoitered
existing facilities on the Crozen Peninsula, and patrolled and
maintained lines in the vicinity of Corps Headquarters.
Thirty-four men proved in sufficient to furnish
communication between a moving Corps and Army. The detachment
was at a decided disadvantage due to lack of supply personnel, and
the same trucks used in laying lines were required for hauling
materials from the depts. In one instance a Quartermaster unit
was provided to haul cable to the detachment.
During the entire month of operations with VIII
Corps there was not a single case of illness or injury among the
men. The detachment rejoined Company B at Braquis, near Etain, on
September 15.
DETACHMENT
WITH XV CORPS
(3 Aug 44-20 Aug 44).
One officer and four teams from Company A
were dispatched to XV Corps on August 3, and joined Corps
Headquarters at Duce. They immediately placed spiral-four
cable to Nattel on the proposed Corps axis. However, Corps did
not move there, so they started placing cable from Fougeres south.
Corps moved to Port Brilot, near St. Ouen, and the cable was
extended to this point.
The detachment aided the 92nd Signal Battalion in
placing cable to the next Corps CP at St. Jean, and immediately
started laying cable from St. Denis east along the Corps axis.
This line was completed through Le Mans to Savigne (28 miles).
Enemy snipers were active in Le Mans at this time.
After Corps' move to Savigne, the detachment
placed spiral-four from Ballon to Louvigny (12 miles), where it
tapped on to an existing open wire lead. This lead was
rehabilitated from Louvigny to Valtrambe, to which point Corps then
moved. Corps continued on to a point west of Paris with the
axis being extended by this detachment and the 92nd Signal
Battalion.
This detachment was definitely too small for the
work to be done with Corps. It was necessary for them to
travel great distances to obtain spiral-four cable, the Corps Signal
Supply did not stock it. The distance between Corps and Army
was frequently too great to insure a talking circuit with the use of
carrier.